Auckland Airport power upgrade
Partnering with Auckland Airport and industry leaders, Northpower is upgrading power infrastructure, including 11kV switchgear to meet growing electricity demand.
Location: Ōmāmari, 12km north‑west of Dargaville
Start date: December 2024
Completion date: December 2026
Project client: Mercury
Annual Report 2026
Northpower was selected to deliver critical electricity infrastructure supporting Mercury’s Kaiwaikawe wind farm at Ōmāmari, north of Dargaville. The project involves constructing the transmission connection from the wind farm to the national grid and modifying sections of the existing network to enable the safe transport of turbine components to site.
This work supports a major renewable energy development for Northland, enabling Mercury’s wind farm to connect into Northpower’s network and on to the national grid, while delivering long‑term network upgrades along key transport routes.
power‑line road crossings permanently modified to enable safe transport of 12 wind turbines
of overhead line built
homes powered
Northpower’s scope includes construction of the transmission line connecting the wind farm to the grid, along with upgrades to the Dargaville substation to manage increased power flows. Electricity generated at Kaiwaikawe will connect into Northpower’s substation near Dargaville before flowing on to the national grid at Maungatapere.
This work draws on Northpower’s specialist transmission capability and proven experience in the delivery of complex infrastructure in rural and remote environments.
A significant and unique element of the project is modifying approximately 190 overhead power‑line road crossings along the turbine transport route. Turbine components were shipped into Whangārei and transported by road to Ōmāmari, requiring permanent changes to the network to allow safe passage of these oversized loads.
Rather than temporary lifts, lines are being raised, relocated or placed underground as part of the Mercury‑funded project, allowing for the safe transportation of the turbines while delivering permanent upgrades to the local network.
Network upgrades and road‑crossing modifications require planned power outages for some customers along the route. In September and early October 2025, works through the Dargaville township were completed, including replacing six poles, raising 13 road crossings and completing additional network maintenance such as crossarm replacements.
By integrating Mercury‑funded works with Northpower’s own maintenance activities, the project is delivering broader network improvements while minimising future disruption.
Kaiwaikawe wind farm is a major renewable investment for Northland and will feature the largest and tallest wind turbines in New Zealand. Through delivery of the transmission connection and permanent network upgrades, Northpower is playing a key role in enabling this development and supporting the region’s transition to renewable energy.
The project demonstrates how strong partnerships and specialist capability can deliver shared outcomes – supporting new generation while strengthening the resilience of the local electricity network.