Auckland Airport power upgrade

Location: Auckland Airport
Start date: June 2025
Completion date: January 2027
Project client: Auckland Airport
Project partners: Accent Limited, Vector, Beca, Ventia, Tranzcivil, The Building Intelligence Group, Cuesko, Quadcom, Hayes Metals, Schneider Electric

Annual Report 2026

Powering future capacity at Auckland Airport

Auckland Airport identified the need to upgrade its power centre intake, the main incoming supply point, to support growing electricity demand driven by terminal development and future load growth. Northpower delivered critical electrical works to replace 11kV switchgear, ensuring the airport’s electricity supply remains resilient, safe and fit for long‑term growth.

Northpower’s scope included civil works for cable installation, removal of the existing switchboard, installation of a new 23‑panel switchboard, and the staged changeover and commissioning of high‑voltage connections. Building refurbishment works were delivered by a separate contractor, requiring close co-ordination across multiple workstreams.

10000

person-hours

8

Northpower staff on site at peak times

1x

23-panel switchboard

Delivering specialist high‑voltage capability in a live airport environment

The upgrade work required highly specialised teams with high‑voltage skills to deliver in an operational airport environment. Works began with detailed planning, service location and soil testing approvals to meet Auckland Airport’s permitting requirements before excavation could commence.

Northpower’s team managed civil installation, switchboard installation, auxiliary and control cabling, and a carefully sequenced commissioning process. A staggered changeover approach allowed individual 11kV cables to be isolated, transferred to the new switchboard and progressively returned to service, to maintain continuity of supply to airport operations.

Commissioning required close alignment and collaboration with Auckland Airport, Vector and Transpower, supported by detailed commissioning and switching plans endorsed by all parties well ahead of outage windows.

Managing health, safety and risk in a complex site

Safety and risk management were central to the project, given the number of contractors on site and the proximity of works to airport offices and operational facilities. Daily pre‑start meetings were used to coordinate activities, manage overlapping work areas and clearly communicate hazards across all parties undertaking work.

Key risks included dependency on building works by other contractors and design constraints identified during construction. Northpower mitigated these risks through regular co-ordination meetings, proactive identification of design gaps, and early engagement with Auckland Airport and Vector to agree alternative solutions before delays could occur.

This collaborative approach enabled the team to recover lost time caused by external delays and to avoid extended outages during critical airport operating periods.

Collaboration delivering long‑term resilience

The power centre intake upgrade is a critical enabling project within Auckland Airport’s broader development programme as one of the largest airports in Australasia. By working closely with the airport, designers, network owners and contractors, Northpower has supported the timely delivery of infrastructure essential to future terminal expansion and to meet the need for increased electricity demand.

Through strong planning, disciplined safety management and proactive problem solving, the project is strengthening the resilience of Auckland Airport’s electricity network and supporting reliable operations for years to come.

More trusted partner case studies and articles...

Complex Transpower foundations

Working with Transpower, Northpower constructed 93 reinforced concrete foundations, using helicopter access to install transmission infrastructure in remote terrain.

Vector’s Helensville overhead refurbishment

With Vector, Northpower refurbished the K05 South Head Road feeder in Helensville, replacing conductors, poles and crossarms to improve reliability.

Extreme weather response for Powerco

Responding to extreme weather events across multiple regions, Northpower teams worked together to restore power and support communities across the lower North Island.