Supporting critical transport infrastructure
Northpower is relocating and reconfiguring Transpower’s transmission infrastructure along the Cambridge–Piarere corridor to support major transport upgrades.
Location: Auckland
Start date: June 2024
Completion date: Stage 1 completion June 2025, Stage 2 completion July 2026
Project client: Transpower
Project partners: CB Civil, Pipeline Civil
Annual Report 2026
Transpower identified a need to proactively replace 45 cable joints on the 220kV cable between the Brownhill and Pakūranga substations in Auckland. We were chosen as the primary contractor to deliver this project. This critical piece of infrastructure maintains the electricity supply into Auckland and Northland. This prudent approach in replacing these joints will ensure the cable operates effectively for the next 30-40 years.
Timelapse of joint bay cable repair
The 10.5km cable traverses both rural and suburban areas of East Auckland, starting in farmland in Whitford, through Dannemora, East Tamaki Heights, Botany into Pakuranga.
Two experienced civil contractors, CB Civil and Pipeline Civil were engaged to deliver the project with Northpower. Transpower engaged an overseas specialist for the cable jointing work. Our responsibilities include co-ordinating the cable jointing and civil work, ensuring the health and safety of 80 on-site personnel in peak times, as well as the public in close proximity to the cable.
The project is being delivered in two phases: June 2024 to June 2025 where 21 cable joints were replaced and June 2025 to July 2026 where 24 cable joints will be replaced. Over 200,000 person-hours have been put towards the delivery of this project so far.
person-hours invested
personnel onsite each day
cable joints along 10.5km of cable

Cable repair requires highly specialised technical skills. First, the site is cordoned off and excavated using a digger or jackhammer if under the roadway. The exposed work area – called a joint bay, is then secured with retaining walls, scaffolding, and waterproof wrap.
To expose the cable joint, rock-breakers remove Fluidised Thermal Backfill (FTB) concrete around the 220kV cables. Extreme care, appropriate work practices and tools are used to avoid damaging the cables.
After the cable joint repairs are complete, the area is restored—the wrap is removed, the joint bay filled with low thermal resistivity material, the earth backfilled, and any impacted roadways repaired.
To ensure a ensure a smooth project delivery for Transpower, Northpower’s project team has effectively addressed and resolved health and safety issues that have emerged during the course of works.
In collaboration with civil contractors and the international specialists, the team has developed several innovative solutions including:
Northpower applies robust safety protocols to keep the public safe at our worksites. Each worksite is cordoned off with large barriers to prevent the public entering a hazardous environment. In cases where the barriers block visibility for motorists, convex safety mirrors and dedicated traffic management is installed to improve visibility.

The project is on track to meet Transpower’s deadlines.
The completion of this project will ensure a reliable supply of electricity to Auckland and Northland, powering economic growth in both regions for the next 30-40 years.